The M12 Motorway is a new 16-kilometre motorway that will provide direct access to Western Sydney International Airport at Badgery’s Creek and connect to Sydney’s existing motorway network.

The toll-free motorway will support future growth in western Sydney while increasing road capacity, reducing congestion, and improving travel times.
Construction work commenced in August 2022 with work scheduled to be complete prior to the opening of the new Western Sydney International Airport in 2026.
A portion of the Parklands adjacent to Elizabeth Drive was acquired by Transport for NSW to construct the M12 Motorway.

During detailed design of the M12, Transport for NSW agreed to relocate the alignment adjacent to Elizabeth Drive, to minimise the impact on the Southern Parklands precinct.

Transport for NSW continues to work with Western Sydney Parklands to minimise the M12 Motorway’s impact on the Parklands.
The M12 Motorway, initially known as Western Sydney Airport Motorway, is an under-construction east-west motorway in Sydney, Australia, linking between the M7 Motorway and The Northern Road, as part of the Western Sydney Infrastructure Plan. Wikipedia
Length: 14 km (8.7 mi)
East end: Westlink M7 (M7); Cecil Park, Sydney
Major suburbs / towns: Cecil Park, Cecil Hills, Mount Vernon, Kemps Creek, Badgerys Creek, Luddenham
Route number(s): M12
West end: The Northern Road (A9); Luddenham, Sydney

All Comments (8)
  • @jackthelab6755
    Great video I cant believe how quick they can build a road when there's no traffic Every couple of weeks i take the bike for a spin at Wylde Mtb and the progress I see at the m7/m12 interchange is unbelievable
  • @PINEx2
    how bloody good is infrastructure
  • Thanks for the vid! It's remarkable just how enormous just one auxiliary part of the project is! The airport is the headline act, but even the support acts are huge!
  • @mitch19636
    Thank you, Col. I live in St Marys. Love watching the progress at the station.